General Contractor

Grand Sierra Resort — 5 Phases

NCTS Corp

Back to Case Studies

1,000+

Hotel Rooms

5

Phases

Stone, Tile, Porcelain

Materials

Challenge

Renovate 1,000+ hotel rooms across 5 phases over multiple years while maintaining consistent quality, material matching, and minimal disruption to ongoing resort operations.

Solution

NCTS established a dedicated project team that remained consistent across all phases. Material procurement was centralized to ensure color and batch consistency. Phased scheduling allowed floors to remain revenue-generating during construction.

Results

All 5 phases completed on time and budget. The resort's management specifically requested NCTS for each subsequent phase based on prior performance.